Home / Block Management / Major Works & Section 20
MAJOR WORKS & SECTION 20

Major Works &
Section 20
Consultation

North, East London & Essex

Done correctly, once. Not started and left for someone else to finish. Section 20 consultation managed from notice of intention through to completion — no shortcuts, no uncollectable costs.

£250
Cap per leaseholder if
Section 20 goes wrong
3
Statutory stages — all
must be completed
60+
Days minimum statutory
consultation period
The Property Institute accredited
Client Money Protection held
Property Ombudsman member

What Section 20 Is and Why It Cannot Be Skipped

Major works are one of the most consequential things a managing agent does on behalf of a residential block. They are expensive, they affect every leaseholder, they require a specific statutory process to be followed before a penny can be recovered through the service charge, and they take months to plan and complete properly.

Get the Section 20 process wrong and the amount recoverable from each leaseholder is capped at £250 — regardless of what the works cost. On a significant external repairs programme or roof replacement, that shortfall can run to hundreds of thousands of pounds. The responsible party — the RTM company, the RMC, or the freeholder — carries the exposure.

We have managed Section 20 major works correctly, from notice of intention through to completion. We have also inherited blocks where the previous agent ran major works for years without finishing them — scaffolding up, costs mounting, leaseholders waiting for an answer that never came. We know what the process is supposed to look like, and we know exactly what it looks like when it goes wrong.

Section 20 of the Landlord and Tenant Act 1985 requires the landlord — in practice, the managing agent acting on their behalf — to consult with leaseholders before carrying out qualifying works where any one leaseholder's contribution will exceed £250. The consequence of not following it correctly: recovery from each leaseholder is capped at £250, regardless of actual cost. For a 20-flat block with £100,000 of external repairs, a failed Section 20 means a maximum recovery of £5,000. The remaining £95,000 cannot be demanded through the service charge.

The £250 cap is not a technicality. It is a hard limit.

We have seen managing agents treat Section 20 as paperwork — something to do alongside the works rather than before them. It is not. The consultation must be completed in the correct sequence, with the correct notices, and the correct time allowed for leaseholder responses. Shortcutting any stage exposes the responsible party to an uncollectable shortfall on the works costs.

The Section 20 Consultation Process

Section 20 qualifying works follow a three-stage statutory consultation process. Each stage has specific requirements and minimum time periods. All three stages must be completed before works can proceed and costs recovered.

1

Stage 1 — Notice of Intention

What it covers: The landlord notifies leaseholders of the intention to carry out qualifying works and gives them the opportunity to nominate a contractor to be invited to tender. The notice must describe the works and invite observations.

Minimum period: 30 days for leaseholders to respond with observations or contractor nominations.

If skipped or wrong: Stage 1 omitted or notices defective — entire process invalid. £250 cap applies.

2

Stage 2 — Notification of Estimates

What it covers: At least two estimates are obtained (including any nominated contractor if one was put forward). Leaseholders are notified of the estimates and invited to make observations. A summary of the estimates must be made available for inspection.

Minimum period: 30 days for leaseholders to respond with observations.

If skipped or wrong: Fewer than two estimates obtained, or leaseholder's nominated contractor not included without good reason — process flawed. Tribunal may disallow recovery above £250.

3

Stage 3 — Notice of Reasons (where required)

What it covers: If the lowest estimate is not chosen, or if a leaseholder's nominated contractor is not appointed, the landlord must give written reasons within 21 days of entering the contract.

Minimum period: Within 21 days of entering the contract.

If skipped or wrong: Failure to provide reasons when required — leaseholders can apply to Tribunal to have the contract set aside or recovery capped.

How We Manage Major Works

We manage the full Section 20 process on behalf of the RTM company, RMC, or freeholder. The works do not begin until the consultation is correctly completed. We do not take shortcuts because the consequences of getting it wrong fall on our clients, not on us.

Works scoping and specification

We establish what the building needs before any contractor is invited to quote. A clear, specific specification is the foundation of a valid tender process and a fair comparison between contractors.

Section 20 notices — all three stages

Notices drafted correctly, served on all qualifying leaseholders, time periods observed. Records maintained of every notice served and every response received. No shortcuts.

Tender management

Minimum two estimates obtained. Leaseholder-nominated contractors invited where relevant. Tender documentation prepared and managed. Responses evaluated on a like-for-like basis.

Director briefing on contractor selection

Tender results presented to directors with our assessment and recommendation. The decision to appoint is made by directors, not by us. Where the lowest estimate is not recommended, we provide written reasons.

Works oversight and supervision

We supervise the works on behalf of the RTM company or RMC. Progress monitored against programme. Variations approved by directors before instruction. Our supervision fee is 10% of works cost — disclosed and agreed before instruction.

Final account and cost reconciliation

On completion, the final account is agreed with the contractor, reconciled against the tender price, and any legitimate variations accounted for. Cost properly attributed to the service charge account.

Inheriting Incomplete Major Works

One of the most difficult situations in block management is taking over a building where major works have been started but not completed by the previous agent. The scaffolding is up. Money has been spent. Leaseholders are waiting.

We are currently managing exactly this situation. External repair works were started under a previous agent. The Section 20 consultation was completed validly — leaseholders know what they agreed to contribute and the statutory recovery position is intact. But the works were not finished when we took over. Our role is to establish the scope of what remains, assess whether the reserve fund covers the outstanding costs, and manage the completion properly, with full transparency to leaseholders throughout.

When we inherit incomplete works we conduct a full assessment of what was done and what remains. We review the Section 20 record to confirm whether the statutory process was correctly completed — because if it was not, the recovery position for outstanding costs may be compromised. We establish the financial position: what has been charged to leaseholders, what the reserve fund holds, and whether additional contributions will be needed.

Transparency throughout is not optional — it is what leaseholders are entitled to. Leaseholders who have been waiting years for works to complete, without clear communication about why or when, are already frustrated. They are entitled to know the financial position, the revised programme, and what the cost to them is likely to be. We provide that information clearly and do not wait to be asked for it.

Common Section 20 Failures and Their Consequences

FailureConsequence
Works begun before Section 20 consultation completed Recovery capped at £250 per leaseholder regardless of actual cost.
Stage 1 notice not served on all qualifying leaseholders Consultation invalid. Process must restart. Works costs at risk.
Fewer than two estimates obtained Consultation flawed. Tribunal may disallow recovery above the cap.
Leaseholder's nominated contractor excluded without reason Leaseholder can apply to Tribunal to have the recovery capped.
Works scope not clearly defined before tendering Variations and cost overruns. Leaseholders charged for work not in the original scope without further consultation.
Works started without director approval of contractor appointment Directors potentially liable for unauthorised expenditure. No valid contract.
Works not completed and new scope not re-consulted Outstanding works costs may not be recoverable if the original Section 20 did not cover the new or remaining scope.
Supervision absent during works. Variations approved without director sign-off Poor quality. Cost overruns. No recourse against contractor. Director liability for unauthorised expenditure.

Major Works Funding: Reserve Fund and Additional Contributions

The best-managed buildings have a reserve fund that has been building towards anticipated major works for years. When the works come, the money is there and the financial impact on leaseholders is manageable. The Section 20 process still applies — the reserve fund does not remove the consultation requirement — but it removes the pressure of having to raise large sums at short notice.

Where the reserve fund does not fully cover the cost of the works, additional contributions are required from leaseholders. These are subject to the same Section 20 consultation process if the total contribution per leaseholder exceeds £250. They are also subject to the Landlord and Tenant Act reasonableness test — leaseholders can challenge the costs at the First-tier Tribunal.

The case for maintaining an adequate reserve fund is straightforward: it reduces the financial shock of major works, reduces the risk of leaseholder challenges, and gives the building a stable financial foundation for its long-term maintenance. We prepare a planned maintenance schedule for every block we manage and set reserve fund contributions accordingly.

Frequently Asked Questions

Section 20 of the Landlord and Tenant Act 1985 requires leaseholders to be consulted before qualifying works are carried out where any single leaseholder's contribution will exceed £250. It applies to most significant maintenance or repair works — external decoration, roof works, structural repairs, lift replacement, and similar. The consultation process involves three stages, specific notices, and minimum time periods for leaseholder responses.
If the Section 20 consultation is not completed correctly — or not completed at all — the amount the landlord can recover from each leaseholder through the service charge is capped at £250, regardless of the actual cost of the works. On a significant works programme, this can leave a very large shortfall that cannot be recovered. The responsible party bears that loss.
Not through Section 20 alone. The consultation process gives leaseholders the right to make observations, to nominate a contractor, and to challenge the reasonableness of costs at the First-tier Tribunal. It does not give them a veto over the works themselves.
The first step is to establish the Section 20 record — was the statutory consultation completed correctly, and does it cover the full scope of what needs to be done? Then we establish the financial position: what has been charged, what the reserve fund holds, and what completing the works will cost. If the outstanding works scope has changed materially from the original Section 20, a fresh consultation may be required for the additional scope.
Our works supervision fee of 10% of the contract value covers the management of the works on behalf of the responsible party — site oversight, progress monitoring, variation management, quality inspection at key stages, and final account negotiation. It does not cover the services of an independent surveyor or project manager, which may be appropriate for larger or more complex works programmes.
There is a dispensation procedure under Section 20ZA of the Landlord and Tenant Act 1985 that allows works to proceed without full consultation in genuine emergencies. Dispensation can be sought from the First-tier Tribunal. Emergency dispensation should not be used as a shortcut for works that are not genuinely urgent.
The statutory consultation process has two 30-day observation periods, which means a minimum of 60 days between serving Stage 1 notices and being in a position to appoint a contractor. In practice, the process typically takes three to four months from beginning Stage 1 to contractor appointment. Works cannot start — and costs cannot be recovered above the £250 cap — until the process is complete.

Planning major works, or dealing with a Section 20 problem?

We manage Section 20 consultation and major works oversight for residential blocks across North, East London and Essex. If you have inherited incomplete works or are unsure about the Section 20 position on your building, start with a conversation.

Call 0208 801 9951  |  info@neonpropertieslondon.co.uk

This website uses cookies. By continuing to use this site, you accept our use of cookies.  Learn more