Home / Compliance Library / Section 20 Consultation
Compliance Library

Section 20 Consultation:
A Complete Guide
for Directors & Leaseholders

The statutory process for consulting leaseholders before major works. Three stages. Hard financial consequences if you get it wrong. Everything RTM directors, RMC boards, freeholders, and leaseholders need to know.

Major Works & Section 20 →
£250
Per-leaseholder cap if
Section 20 is not followed
3
Statutory stages —
all must be completed in order
60+
Minimum days for the
consultation process

Key facts at a glance

Section 20 of the Landlord and Tenant Act 1985 requires leaseholders to be consulted before qualifying works above £250 per leaseholder
Three-stage statutory process: Notice of Intention, Notification of Estimates, Notice of Reasons (where required)
Each of stages 1 and 2 carries a 30-day minimum observation period for leaseholder responses
Non-compliance caps recovery at £250 per leaseholder per qualifying works project — regardless of actual cost
Also applies to qualifying long-term agreements above £100 per leaseholder per year
Dispensation available in genuine emergencies — requires application to the First-tier Tribunal

The Cost of Getting Section 20 Wrong

Section 20 of the Landlord and Tenant Act 1985 is the statutory requirement to consult with leaseholders before carrying out qualifying works or entering into qualifying long-term agreements where the cost to any individual leaseholder will exceed the relevant threshold. It is one of the most important procedural obligations in leasehold management — and one of the most commonly mishandled.

The consequence of getting it wrong is not a warning or an administrative adjustment. It is a hard financial cap on what can be recovered from leaseholders through the service charge, regardless of the actual cost of the works. On a significant external repairs programme or roof replacement, a failed Section 20 process can leave a shortfall of tens or hundreds of thousands of pounds that cannot be recovered.

This guide sets out the full Section 20 consultation process, what it requires at each stage, the common failures and their consequences, how dispensation works, and what leaseholders are entitled to do if the process has not been followed correctly.

What Section 20 Covers

Section 20 consultation is required in two distinct situations.

Qualifying works

Works on a building or any part of it where the cost borne by any single leaseholder will exceed £250. This threshold applies per leaseholder, per works project.

Example: A block of 20 flats with works costing £100,000 — individual contributions of £5,000 each. Well above the threshold. Section 20 required.

Qualifying long-term agreements

Agreements entered into by the landlord for a term of more than 12 months where the cost to any individual leaseholder in any 12-month period will exceed £100.

Covers: Management contracts, maintenance contracts, long-term service agreements — not just one-off works.

The threshold applies per leaseholder, not to the total cost. A common misunderstanding is to compare the total works cost against the £250 threshold. On a block where costs are shared equally, the threshold is breached when the total cost exceeds £250 multiplied by the number of leaseholders.

The Three-Stage Section 20 Process

All three stages must be completed correctly and in sequence. The stages cannot be run concurrently or in the wrong order. Works cannot begin — and costs above £250 per leaseholder cannot be recovered — until the process is correctly completed.

1 Stage

Notice of Intention

The landlord notifies all leaseholders of the intention to carry out qualifying works. The notice must describe the proposed works, invite observations, and invite leaseholders to nominate a contractor to be included in the tender process. Must be served on every qualifying leaseholder and, where there is a recognised tenants' association, on the association.

Observation period

Minimum 30 days for leaseholders to respond with observations or contractor nominations.

If missed or defective

Stage invalid. Entire consultation must restart. £250 cap applies to any costs already incurred.

2 Stage

Notification of Estimates

The landlord obtains at least two estimates — one must be from a contractor not connected to the landlord. If a leaseholder nominated a contractor at Stage 1, that contractor must be invited to tender unless there is a good reason not to. A statement setting out the estimates, together with relevant observations received at Stage 1, must be sent to all leaseholders and made available for inspection.

Observation period

Minimum 30 days for leaseholders to respond with observations on the estimates.

If missed or defective

Fewer than two estimates, nominated contractor excluded without reason, or statement not provided — Tribunal may disallow recovery above £250.

3 Stage

Notice of Reasons (where required)

If the landlord does not choose the lowest estimate, or does not appoint a leaseholder-nominated contractor, written reasons must be provided to all leaseholders within 21 days of entering the contract. Not required if the lowest estimate is chosen and there was no nominated contractor, or if the nominated contractor was appointed.

Timeframe

Within 21 days of entering the contract.

If missed or defective

Failure to provide reasons when required — leaseholders can challenge the appointment. Recovery above £250 may be at risk.

Section 20 for Long-Term Agreements

The process for qualifying long-term agreements differs slightly from the qualifying works process. Stage 1 requires a notice of intention describing the proposed agreement, inviting observations, and inviting leaseholders to nominate a person from whom the landlord should try to obtain a proposal. Stage 2 requires a notice providing at least two proposals, together with observations received at Stage 1.

Long-term agreements that have not been through the correct Section 20 process are qualifying agreements under which the landlord cannot recover more than £100 per leaseholder per year through the service charge. For a management contract or a multi-year maintenance agreement, this can be highly restrictive.

The £250 Cap: What It Means and Why It Matters

If the Section 20 consultation process is not followed correctly — or not followed at all — the amount recoverable from each leaseholder through the service charge is capped at £250 per qualifying works project, regardless of the actual cost.

Real-world example — 20-flat block

£200,000
Actual cost of works
£5,000
Maximum recoverable
(20 × £250)

£195,000 unrecoverable. Falls on whoever was responsible for managing the Section 20 process.

The £250 cap cannot be waived by leaseholders. Even if individual leaseholders are willing to pay their full share, the cap applies as a matter of statute. The only route around the cap — short of completing a fresh Section 20 process for any remaining works — is to apply to the First-tier Tribunal for dispensation.

Common Section 20 Failures and Their Consequences

FailureConsequence
Works begun before Stage 1 notice servedRecovery capped at £250 per leaseholder for entire project. No retrospective fix.
Stage 1 notice not served on all qualifying leaseholdersConsultation invalid for those leaseholders. Process may need to restart. Cap applies.
Stage 1 notice does not describe the works with sufficient particularityNotice defective. Leaseholders can challenge at Tribunal. Cap may apply.
Fewer than two estimates obtained at Stage 2Consultation flawed. Tribunal may disallow recovery above cap.
Leaseholder's nominated contractor not invited to tender without good reasonLeaseholder can apply to Tribunal. Recovery above £250 at risk.
Stage 2 statement not provided to leaseholders for inspectionProcess defective. Observations period not validly commenced.
30-day observation period not allowed at either stageProcess invalid. Works cannot validly proceed on full cost recovery basis.
Lowest estimate not chosen and no written reasons given within 21 daysStage 3 non-compliance. Leaseholders can challenge the appointment.
Works materially different from those described in Stage 1 noticeNew consultation required for the different works. Costs for undescribed works capped.
Section 20 started but not completed before works beginSame as never starting — cap applies to costs incurred before completion of the process.

Dispensation: When Section 20 Can Be Bypassed

Section 20ZA of the Landlord and Tenant Act 1985 allows the First-tier Tribunal to grant dispensation from all or any of the Section 20 consultation requirements. Dispensation is not automatic and is not available simply because consultation is inconvenient or time-consuming.

When it is appropriate

Genuine emergency — works urgently needed to prevent immediate danger or serious damage where waiting 60+ days would cause significantly greater harm. Roof collapse, structural failure, major water ingress.

Retrospective dispensation

Dispensation can be sought after the fact — where works were carried out without Section 20 compliance. Harder to obtain. The Tribunal assesses whether the failure to consult caused any prejudice to leaseholders.

How to apply

Application to the First-tier Tribunal (Property Chamber). Must set out the works, explain why Section 20 requirements were not or cannot be met, and demonstrate why dispensation should be granted.

Emergency dispensation is not a shortcut for works that are merely urgent. The Tribunal distinguishes between works that are genuinely immediately dangerous — where dispensation is appropriate — and works that are merely time-sensitive or overdue. Misusing the dispensation process exposes the responsible party to costs and an adverse Tribunal finding.

Your Rights If Section 20 Was Not Followed

If you are a leaseholder and you believe the Section 20 process for works on your building was not correctly followed, you have specific rights.

Your rightWhat it means
Challenge the service charge at the First-tier Tribunal You can apply to the Tribunal for a determination that the service charge is not payable, or not payable above the £250 cap, on the basis that Section 20 was not followed. The Tribunal can disallow recovery above the cap.
Withhold the disputed portion while proceedings are ongoing You can withhold the portion of the service charge demand above £250 that you dispute, while Tribunal proceedings are ongoing. Take legal advice on how to do this correctly to avoid arrears proceedings.
Request a summary of costs and inspect accounts You are entitled to request a written summary of the costs and to inspect the accounts, receipts, and relevant documents. This allows you to assess whether Section 20 was required and whether it was followed.
Make observations during the consultation If Section 20 is being run now, you have the right to make observations at Stage 1 and Stage 2, and to nominate a contractor at Stage 1. Your observations must be considered.
Apply to the Tribunal if your nominated contractor was excluded If you nominated a contractor at Stage 1 and they were not invited to tender without good reason, you can apply to the Tribunal to challenge the appointment made.

Take legal advice before withholding service charge payments. Withholding service charge payments carries risk even where there is a genuine Section 20 dispute. If your challenge is unsuccessful, or if the amount withheld was not properly calculated, you may face arrears proceedings and associated costs.

Frequently Asked Questions

Section 20 of the Landlord and Tenant Act 1985 requires the landlord to consult with leaseholders before carrying out qualifying works where the cost to any single leaseholder will exceed £250, or before entering into qualifying long-term agreements where the cost to any single leaseholder will exceed £100 per year. The consultation process has three stages and must be completed before works begin or the agreement is entered into.
If the Section 20 consultation process is not correctly followed, the amount recoverable from each leaseholder through the service charge is capped at £250 per qualifying works project, regardless of the actual cost. The responsible party — the landlord, RTM company, or RMC — bears the shortfall. This is not a proportionate penalty — on a large works programme it can mean the majority of costs are irrecoverable.
No. The Section 20 process gives leaseholders the right to make observations, to nominate contractors, and to challenge unreasonable costs at the First-tier Tribunal. It does not give leaseholders a veto over whether the works proceed. A landlord who has correctly completed the Section 20 process can proceed with the works even if leaseholders objected during the consultation.
The minimum time from serving Stage 1 notices to being in a position to appoint a contractor is 60 days — two 30-day observation periods running consecutively. In practice, the process typically takes three to four months from beginning Stage 1 to contractor appointment, factoring in time to obtain estimates and the notice drafting and service process.
If works are genuinely immediately dangerous and waiting for the Section 20 consultation process would cause significantly greater harm, dispensation can be sought from the First-tier Tribunal under Section 20ZA of the Act. Dispensation should be applied for as soon as the emergency is identified — not after the works are completed. If dispensation is not obtained and the works proceed without consultation, the £250 cap applies regardless of the urgency.
The first step is to establish whether the Section 20 record is complete and valid for the works carried out to date. If Stage 1 and Stage 2 were correctly completed before works began, the recovery position for those works is intact. If the works scope has changed materially from what was described in the notices, or if the process was incomplete when works began, specialist legal advice should be taken. For any remaining or new works, a fresh Section 20 process is required if costs will exceed the threshold.
Yes. At Stage 1 of the Section 20 process, leaseholders are invited to nominate a contractor to be included in the tender process. If you nominate a contractor, the landlord must invite that contractor to tender unless there is a good reason not to — for example, the contractor is unwilling, unable to do the work, or not appropriately qualified or insured. If your nominated contractor is excluded without good reason, you can challenge this at the First-tier Tribunal.
No. Section 20 applies to works on the building or any part of it that are funded through the service charge. Works carried out by a leaseholder inside their own flat at their own expense are not qualifying works. However, if the landlord is contributing to works inside flats — for example, internal communal works or works to shared services running through flats — Section 20 may apply depending on how the costs are treated.

Managing a Section 20 process, or dealing with one that went wrong?

We manage Section 20 consultation and major works for residential blocks across London and Essex. If you have inherited incomplete works or are unsure about the Section 20 position on your building, start with a conversation.

Call 0208 801 9951  |  info@neonpropertieslondon.co.uk

This website uses cookies. By continuing to use this site, you accept our use of cookies.  Learn more