Section 20 Consultation: The Complete Guide for RTM Directors

Section 20 of the Landlord and Tenant Act 1985 is one of the most practically important pieces of legislation that RTM directors deal with. It requires landlords — and RTM companies acting in the landlord's management role — to consult leaseholders before carrying out qualifying works above a certain cost, or before entering into qualifying long-term agreements. Skip it, or get the process wrong, and the amount recoverable through the service charge is capped at the qualifying threshold — regardless of what the works actually cost. This guide covers everything RTM directors need to know: what triggers it, the financial thresholds, the two-stage process for both types of qualifying expenditure, the emergency exemption, dispensation, and the most common mistakes.

📅 Published: 20 October 2026 ⏱ 14 min read 🏷 Block Management 👤 Neon Property Services

Quick Answers

Q1

What triggers Section 20?

Two triggers: qualifying works (any one leaseholder contributes more than £250) and qualifying long-term agreements (contracts over 12 months where any one leaseholder contributes more than £100 per year). Both apply to RTM companies in the same way they apply to landlords. The thresholds are per leaseholder — in a 20-flat block with equal shares, any annual contract costing over £2,000 triggers the qualifying agreement threshold.

Q2

How long does the consultation take?

A minimum of 30 days per consultation stage, with two stages required for most qualifying expenditure. For qualifying works, the full process takes approximately 60 days minimum — 30 days for the Notice of Intention observation period, then at least one round of contractor tendering, then 30 days for the Notice of Proposal observation period. For qualifying long-term agreements, the same two-stage structure applies.

Q3

What happens if consultation is skipped?

Recovery through the service charge is capped at the qualifying threshold — £250 per leaseholder for works, £100 per year per leaseholder for long-term agreements. In a 20-flat block with a £60,000 major works programme (£3,000 per leaseholder), skipping consultation limits recovery to £250 per leaseholder — a £55,000 shortfall that the RTM company cannot recover.

At a Glance

Why Section 20 exists: before the Landlord and Tenant Act 1985 introduced mandatory consultation, landlords could carry out expensive works and charge the full cost to leaseholders through the service charge with no prior warning, no opportunity to obtain competing quotes, and no ability to comment on the proposed contractor or cost. Section 20 addresses this by requiring the landlord (or RTM company) to tell leaseholders what is proposed and why, invite them to nominate a contractor, and give them an opportunity to comment on the proposed contractor before the contract is awarded. It is a transparency and accountability mechanism, not simply an administrative hurdle.

Why it matters for RTM companies specifically: an RTM company that carries out significant works or enters significant contracts without following the Section 20 process is not just technically in breach — it is exposing its directors to personal liability for the unrecoverable shortfall if the service charge cap kicks in. Where a £60,000 major works programme is carried out without consultation and recovery is capped at £5,000 (20 leaseholders x £250), the remaining £55,000 has to come from somewhere. If the RTM company's funds are insufficient, the shortfall may fall on the directors personally. RTM directors who treat Section 20 as optional paperwork rather than a legally binding obligation are taking a serious personal financial risk.

Key Takeaways

01

The thresholds are per leaseholder — small blocks hit them quickly

The £250 qualifying works threshold and the £100 qualifying agreement threshold apply per leaseholder, not to the total cost. In a small block of six flats with equal service charge shares, any annual maintenance contract costing more than £600 (6 x £100) per year triggers the qualifying agreement consultation. Most communal cleaning contracts, grounds maintenance contracts, and lift servicing contracts in even the smallest blocks will exceed this threshold. Treating Section 20 as something that only applies to large blocks or major works is a common and expensive misconception.

02

Leaseholder nominations must be honoured — but the nominee can still be rejected on merit

Where a leaseholder nominates a contractor during the Notice of Intention observation period, the landlord or RTM company must invite that contractor to tender. This is mandatory — not discretionary. However, the obligation is to invite, not to appoint. The nominated contractor is evaluated against the same criteria as all others and can be rejected if their price or quality is not competitive. Where the RTM company does not appoint the nominated contractor, the Notice of Proposal must specifically explain why the nominated contractor was not selected. The Tribunal will expect this explanation to be substantive, not formulaic.

03

The observations in the consultation must be genuinely considered — not just read

Leaseholders who make observations during either stage of the consultation are entitled to a written response within 21 days of the end of the observation period (or, in the case of the Notice of Proposal, before the contract is entered into). The response must actually address the observations made — not simply acknowledge receipt. Where a leaseholder nominates a contractor or raises a specific concern about a proposed contractor's price or track record, that concern must be addressed on its merits. A Tribunal that later examines the consultation file and finds that leaseholder observations were collected but not meaningfully considered may find that the consultation was not validly carried out.

04

The cheapest tender does not have to be accepted — but the reason must be documented

Where the RTM company does not propose to accept the lowest tender in the Notice of Proposal, the notice must state the reasons why. This is a statutory requirement, not a best-practice recommendation. Where a nominated contractor's tender is cheaper than the proposed contractor and the RTM company is not proposing to accept the nominated tender, the reasons must be even more specifically explained. The Tribunal has found that reasons which are not genuinely substantiated — for example, citing the proposed contractor's "experience" without any specific evidence — are not sufficient.

05

Section 20 applies to agreements, not just works — and is often missed for contracts

The qualifying works trigger is relatively well-known. The qualifying long-term agreement trigger — which applies to any maintenance contract lasting more than 12 months where any leaseholder contributes more than £100 per year — is less well understood and is frequently missed. An RTM company that appoints a lift maintenance contractor on a two-year contract without Section 20 consultation, because it thinks of Section 20 as relevant only to major works, is in the same legal position as one that carries out a major works programme without consultation. The financial consequences are the same: recovery capped at £100 per leaseholder per year.

06

Dispensation is available — apply for it early, not as an afterthought

The First-tier Tribunal can grant dispensation from the Section 20 requirements where it is reasonable to do so. Dispensation applications are most likely to succeed where the works were genuinely urgent, where the failure to consult was inadvertent and leaseholders have not been prejudiced, and where the RTM company has acted in good faith throughout. The worst time to apply for dispensation is after a leaseholder has made a Tribunal application challenging the service charge on Section 20 grounds. The best time is as soon as the RTM company becomes aware that it has not followed the process correctly — ideally before any demand for payment has been made.

The Two Triggers: Qualifying Works and Qualifying Long-Term Agreements

Section 20 is triggered by either of two types of expenditure. They have different thresholds, different consultation processes, and different consequences for non-compliance. Understanding which trigger applies is the essential first step in every Section 20 analysis.

  • Qualifying works: works on a building or any other premises. Works include building, repairing, maintaining, improving, or renewing the building or any part of it. They include both planned maintenance and reactive repairs above the threshold. The trigger is crossed when any one leaseholder would contribute more than £250 to the cost of the works.
  • Qualifying long-term agreements (QLTAs): agreements with a term of more than 12 months entered into by the landlord (or RTM company) in connection with the management of a building or the provision of services. This includes most maintenance contracts (cleaning, grounds, lift servicing, fire alarm maintenance), managing agent agreements, and insurance contracts. The trigger is crossed when any one leaseholder would contribute more than £100 per year under the agreement.
⚠️ Both triggers can apply simultaneously

Where an RTM company enters into a two-year contract for the supply and maintenance of a new CCTV system, both triggers may apply simultaneously. The installation element may constitute qualifying works (if any leaseholder's share exceeds £250); the ongoing maintenance element may constitute a qualifying long-term agreement (if any leaseholder's annual contribution exceeds £100). Where both apply, the RTM company must comply with the consultation process for both — which in practice often means combining the processes, but care must be taken that both sets of requirements are satisfied.


The Financial Thresholds

Qualifying Works

One-off works to the building
£250

The maximum any one leaseholder can be required to contribute to qualifying works without prior Section 20 consultation. If any leaseholder would pay more than this, consultation is required before the works are carried out.

Example: 20-flat block, equal shares. External redecoration costs £40,000. Each leaseholder's share = £2,000. This is well above £250 — Section 20 consultation is required.

Qualifying Long-Term Agreements

Contracts lasting more than 12 months
£100

The maximum any one leaseholder can be required to contribute per year to a qualifying long-term agreement without prior Section 20 consultation. If any leaseholder would pay more than this per year, consultation is required before the contract is entered into.

Example: 10-flat block, equal shares. Lift maintenance contract costs £6,000/year. Each leaseholder's annual share = £600. This is above £100 — Section 20 consultation is required before the contract is signed.

The Section 20 Process for Qualifying Works

Qualifying works require a two-stage consultation process. Both stages must be completed before the works contract is entered into.

Stage 1 — Notice of Intention

Served before tendering begins

The Notice of Intention must be given to every leaseholder (and any recognised tenants' association) in writing before any tender documents are issued to contractors. It must:

  • Describe in general terms the proposed works
  • State why the RTM company considers the works necessary
  • Invite observations within a 30-day observation period
  • Invite leaseholders to nominate a contractor to be invited to tender

Observations received must be considered and responded to in writing within 21 days of the end of the observation period. Any contractor nominated by a leaseholder must be invited to tender.

⏱ Observation period: 30 days minimum

Stage 2 — Notice of Proposal (Estimates)

Served after tenders received, before contract awarded

Once tenders have been obtained — including from any nominated contractor — a Notice of Proposal must be given to every leaseholder before the contract is awarded. It must:

  • Set out the estimates or proposals obtained (including the nominated contractor's estimate if received)
  • State the name and address of the proposed contractor
  • State the reasons for the proposed contractor being selected where it is not the lowest estimate or the nominated contractor's estimate
  • Invite observations within a 30-day observation period

The contract must not be awarded until after the 30-day observation period has expired. All observations received must be considered. The RTM company is not obliged to accept the lowest tender but must explain why it is not doing so.

⏱ Observation period: 30 days minimum — no contract until period expires

The Section 20 Process for Qualifying Long-Term Agreements

Qualifying long-term agreements (contracts lasting more than 12 months) follow a similar two-stage process, with one important addition: there is a third stage where the agreement is for works and services together, or where the Tribunal's dispensation has been obtained.

Stage 1 — Notice of Intention

Served before any tendering process begins

Identical in structure to the qualifying works Notice of Intention. It must describe the proposed agreement in general terms, state why it is considered necessary, invite observations within 30 days, and invite leaseholders to nominate a contractor to be invited to tender. Any nomination received must be taken up and the contractor invited to tender.

⏱ Observation period: 30 days minimum

Stage 2 — Notice of Proposal

Served after tenders received, before contract awarded

After tenders have been obtained, a Notice of Proposal must be given to every leaseholder. It must:

  • Set out the proposals received (at least two independent quotes, plus any nominated contractor's quote)
  • State the name of the proposed contractor and why they were selected, specifically addressing why any cheaper tender was not accepted and why any nominated contractor's tender was not accepted
  • Invite observations within a 30-day observation period

The agreement must not be entered into until after the 30-day period expires. All observations must be considered and responded to in writing. Where the RTM company intends to appoint a contractor other than the cheapest or the nominated contractor, the Notice must provide specific and substantiated reasons.

⏱ Observation period: 30 days minimum — no contract signed until period expires

Consequences of Non-Compliance

Scenario Legal position Financial impact
Qualifying works carried out without any consultation Recovery from any leaseholder is capped at £250, regardless of actual cost. No leaseholder can be required to pay more than £250 toward the works through the service charge. In a 20-flat block with £60,000 works (£3,000/leaseholder), the RTM company can only recover £5,000 (20 x £250). The remaining £55,000 cannot be recovered through the service charge.
Qualifying long-term agreement entered without consultation Recovery from any leaseholder under that agreement is capped at £100 per year. The contract remains valid and the contractor must be paid — but the service charge recovery is limited. For a £12,000/year cleaning contract in a 20-flat block (£600/year per leaseholder), the RTM company can only recover £2,000/year (20 x £100). The remaining £10,000/year must be funded from elsewhere.
Stage 1 (Notice of Intention) not served, but Stage 2 was The consultation was not validly carried out — both stages are required. The position is the same as if no consultation was carried out. Same recovery cap applies — £250 per leaseholder for works, £100 per year for agreements.
Notice of Intention not given to all leaseholders Leaseholders who did not receive the notice are in the same position as if no consultation occurred — the cap applies to their contribution. Leaseholders who did receive valid notices may be charged in full. Partial recovery cap: leaseholders who received valid notices pay in full; those who did not are capped at £250/£100. Managing the split can be complex and contentious.
Works carried out and consultation started retrospectively Retrospective consultation does not cure the failure to consult before the works were carried out. The only route to recovery above the cap at this point is a dispensation application to the Tribunal. Until dispensation is granted (if it is), the cap applies. If dispensation is refused, the capped amounts are the maximum recoverable regardless of how much was spent.

Emergency Works Exemption

Where qualifying works are urgently needed and it is not reasonably practicable to comply with the full Section 20 consultation process before carrying out the works, the emergency works exemption applies. This allows the works to be carried out and the cost to be recovered in full through the service charge, without the prior two-stage consultation.

For the exemption to apply:

  • The works must be genuinely urgent — necessary to prevent serious risk to health, safety, or the building, where the standard 60-day minimum consultation timetable would cause unacceptable delay or harm
  • It must not be reasonably practicable to comply with the consultation requirements before carrying out the works
  • The landlord or RTM company must notify all leaseholders as soon as reasonably practicable after the emergency that the works have been or are being carried out, describe the works and their urgency, and invite observations within 30 days
🚨 The emergency exemption is not a shortcut for planned works

The emergency exemption is for genuine emergencies — a burst main flooding communal areas, a lift failure creating a risk to elderly or disabled residents, structural damage from a vehicle collision. It is not available for works that were known to be needed weeks or months ago but where the consultation was simply not started in time. Where a roof repair has been on the managing agent's maintenance plan for two years, it cannot be carried out under the emergency exemption because the RTM company has left it too late to consult. In that situation, the options are to carry out the consultation (accepting that works may be delayed), to apply for a dispensation, or to carry out the works without consultation and face the recovery cap.


Applying for Dispensation

Under Section 20ZA of the Landlord and Tenant Act 1985, the First-tier Tribunal has power to dispense with all or any of the Section 20 requirements if it is satisfied that it is reasonable to do so. Dispensation does not require the landlord to have acted unreasonably — the Tribunal assesses whether it would be reasonable in all the circumstances to waive the consultation requirements.

Factors the Tribunal considers in a dispensation application:

  • Whether leaseholders have been prejudiced by the failure to consult — in particular, whether they were deprived of the opportunity to nominate a contractor who might have provided better value
  • The reasons for the failure to consult — genuine urgency, inadvertent error, or deliberate avoidance are treated differently
  • Whether the cost incurred was reasonable regardless of the consultation failure
  • Whether leaseholders have been given any opportunity to comment, even retrospectively

Dispensation is most commonly granted where:

  • The works were genuinely urgent but did not meet the strict emergency works exemption criteria
  • The consultation failure was inadvertent and the works were competitively procured
  • Leaseholders have been given the opportunity to make observations retrospectively and have either not done so or have not raised substantive concerns about value for money

Apply for dispensation as soon as you become aware of the consultation failure — before any demand for payment is made if possible. Applying after a leaseholder has already made a Tribunal application challenging the charge on Section 20 grounds is not impossible, but it weakens the RTM company's position significantly.


Common Section 20 Mistakes to Avoid

Applying the threshold to the total cost, not per leaseholder

The £250 and £100 thresholds apply per leaseholder, not to the total contract value. Managers who check whether the total cost exceeds £250 — rather than each leaseholder's share — will miss the trigger in large blocks where individual shares are modest but the total is substantial. Always calculate the per-leaseholder share using the service charge proportions in the leases.

Starting works before the Stage 2 observation period expires

The contract must not be awarded and works must not commence until the Stage 2 (Notice of Proposal) 30-day observation period has expired. Awarding the contract on day 28 because the contractor is available and leaseholders "haven't raised any objections yet" invalidates the consultation. The 30 days must run in full regardless of whether observations are received.

Not inviting a leaseholder-nominated contractor to tender

Where a leaseholder nominates a contractor during the Stage 1 observation period, inviting them to tender is mandatory — not discretionary. Failing to do so invalidates the consultation even if all other steps were followed correctly. If the nominated contractor declines to quote or cannot be contacted, document this carefully as evidence that the obligation to invite them was discharged.

Not explaining why the cheapest tender was not accepted

The Stage 2 Notice of Proposal must specifically state the reasons why the cheapest tender is not being accepted, where that is the case. A generic statement ("the proposed contractor was selected on the basis of quality and experience") is not sufficient. The reasons must be specific and capable of being verified — specific qualifications, specific references, specific evidence of relevant experience.

Treating annual contracts as not qualifying because they are "rolling"

A contract that is technically for 12 months but is expected to be renewed automatically each year is often treated as an annual contract not requiring Section 20 consultation. Where the contract is renewed each year, this is correct — each 12-month contract individually does not exceed the qualifying term. But where the arrangement is in substance a long-term engagement that happens to be documented in annual renewals, the Tribunal may look through the form to the substance. Genuinely annual contracts that are not expected to continue do not require consultation; long-term arrangements documented in annual renewals to avoid consultation may still be found to be qualifying agreements.

Not keeping the consultation file

The entire Section 20 consultation file — both Notices, all observations received, written responses to observations, all tenders obtained, the evaluation record, and the appointment confirmation — should be retained for a minimum of six years. This file is the RTM company's evidence that the consultation was properly carried out if a leaseholder later challenges the service charge. A consultation file assembled from memory after a challenge has been made is far less credible than one that was maintained contemporaneously throughout the process.

📖 Related Reading

For how the competitive tender process that Section 20 requires also generates the documentation that defends service charge challenges, see How to Run a Competitive Tender for Block Maintenance Contracts. For how Section 20 failures are treated at the First-tier Tribunal, see Leasehold Service Charge Disputes: How the First-tier Tribunal Works. For how Section 20 applies specifically to the service charge budget and reserve fund expenditure, see How to Set Your Block's Service Charge Budget for 2027.


Frequently Asked Questions

Two triggers: qualifying works where any one leaseholder would contribute more than £250, and qualifying long-term agreements (contracts over 12 months) where any one leaseholder would contribute more than £100 per year. Both apply to RTM companies. The thresholds are per leaseholder — in a 20-flat block with equal shares, any works costing over £5,000 total or any annual contract costing over £2,000 total will trigger the relevant threshold. Both triggers can apply to the same project simultaneously where it involves both works and an ongoing maintenance element.

Recovery through the service charge is capped at the qualifying threshold: £250 per leaseholder for works, £100 per year per leaseholder for long-term agreements. This is not a penalty — it is a hard cap on what can be demanded. The works still need to be paid for and the contract still needs to be honoured, but the RTM company cannot recover above the cap through the service charge regardless of actual cost. For major works, this shortfall can be enormous. The only route to recovery above the cap without consulting is a dispensation application to the First-tier Tribunal.

Yes — under Section 20ZA, the First-tier Tribunal can dispense with all or any of the requirements where it is reasonable to do so. Dispensation is most likely to be granted where works were genuinely urgent, the failure to consult was inadvertent, the works were competitively procured at a fair price, and leaseholders have not been prejudiced. Apply for dispensation as soon as the failure to consult is identified — ideally before payment demands are issued. Applying only after a leaseholder challenge has been made is possible but significantly weakens the position.

A description in general terms of the proposed works or agreement; the reasons why they are considered necessary; an invitation for written observations within the 30-day period; and an invitation to nominate a contractor to be invited to tender (for qualifying long-term agreements). It must be given individually to every leaseholder in writing — posting on a notice board is not sufficient. Any recognised tenants' association must also be notified. Observations received must be acknowledged and responded to in writing within 21 days of the end of the observation period.

Not in the same form. Where works are genuinely urgently needed and it is not reasonably practicable to consult before carrying them out, the full Section 20 process can be bypassed. However, leaseholders must be notified as soon as reasonably practicable after the emergency, with a description of the works and their urgency, and given 30 days to make observations. The emergency exemption is for genuine emergencies only — works that were planned but left too late to consult are not emergencies. The exemption should never be used as a routine shortcut for planned qualifying works.

Has your block carried out qualifying works or entered maintenance contracts without completing Section 20?

Neon carries out Section 20 consultation as a standard part of every qualifying works programme and contract appointment — both Notices, complete documentation, and a managed observation process. If your previous agent has entered contracts without consulting, talk to us about assessing your position and the dispensation options available.